Modernization of Kutaisi Bypass Road – Samtredia Section in to 4-lane Motorway, km 30+000 – km 41+354, Lot 4.
Construction of the Kutaisi bypass road in western Georgia into a four-lane highway will be completed by the end of 2020. Work on the road began in May, 2019 and aims to add two new lanes to the existing two-lane road. As a result traffic will become one-sided at the Kutaisi-Samtredia bypass road.
Main Data
- Project Start Date: April, 2018
- Project duration: 15 months
- Road length: 11.354 km
- Total volume of earth works – 745 000 m3
- Bridges – 6 930 m2
- Number of employees: 250
- Project cost: 18 million GEL